Future Power Projects

Granny Smith Mining

Granny Smith Mining

Project Duration:  January 2022 to July 2022
Estimated Project Value:  $ 2.5 million

The project included the supply, installation and commissioning of the following:

  • 2.6km of 33kV Powerline
  • 1.7km of 11kV Powerline
  • 1km of 11kV Spur Lines and T Off’s
  • 7km of 48C ADSS Fibre Optic Cable
  • 33kV/11kV 2MVA Kiosk Substation and associated power control cables
  • Trenching and Installation of HV Cables
  • Kiosk Earth Grid Installation
  • 630A 33kV ABS
  • 800A 33kV Recloser
  • 11kV/415V Transformer and associated hardware
  • 15.5m 24kN Galvanised Steel Poles
  • 19/3.75 Pluto Conductor
  • 6/1/3.75 Banana Conductor
  • Removal of 5.1km of Overhead Powerline and transportation off site.
  • Backfill and compaction of areas excavated as part of site works and pole removal.

This project was completed in accordance with the planned schedule with zero incidents.