Telfer Gold Mine – Powerline Maintenance & Reporting

Telfer Gold Mine – Powerline Maintenance & Reporting

Future Power WA was engaged to supply plant and labour for remedial works to the interconnect power system during a planned shutdown.

The works included:

  • Site visit to assess the condition of the interconnect line and to advise of the remedial action required.
  • Supply of a complete safety methodology which included including a breakdown of each task, as well as plant and equipment requirements.
  • Supply and installation of industry approved line products and hardware.
  • Supply manning, plant and equipment to complete all remedial works within a planned 24-hour mine shutdown/power outage.
  • Switch maintenance, HV cable repairs, Recloser testing, reporting and maintenance, hot joint repairs and re-lugging, cleaning, testing and reporting on condition of aerial apparatus including recommendations for future remedial works and maintenance.

The project was completed on time, on budget and without incident.