Future Power WA worked closely with Western Power representatives to design and install the Electrical wiring to three emergency response temporary Power and Communication trailers.

A 50m pole was manufactured by our partner Future Engineering & Communication on behalf of Western Power. Future Power WA was contracted to carry out the installation of the pole, and uplift the conductors to their new positions. This project involved detailed and comprehensive planning in conjunction with Western Power to ensure the line was out of service for the minimum time possible. The line also crossed over two major arterial roads. The project was completed within the planned outage time with no incidents and to the complete satisfaction of Western Power. Western Power can be found at https://westernpower.com.au/